Electric Project Updates

New Three Phase
Install new three phase primary underground cable to SMU water well 12 on east side of the airport
Scheduled for 2016

Underground Conversion
Three phase OH to UG primary conversion along 1st Avenue SE 900-1000 blocks
Completed 2015

New Service
New primary electric service in Green Industrial Park (Three phase UG primary extension) for Black Hills Energy
Completed 2015

Replace Overhead Line
Rebuild overhead 69kV transmission line from the center substation to the east substation along East Milwaukee Street
Completed 2015

Development
Install new single phase primary underground cable in Gateway by IGL First Addition
Completed 2015

SCADA Upgrade
Electric System Supervisory Control and Data Acquisition (SCADA) Upgrade
Completed 2015

Parking Lot Lights
Lights installed in Spencer Public Library parking lot
Completed 2015

Underground Replacement
Replace a stretch of old three phase existing primary underground cable with new along 2nd Avenue East between East 9th Street and East 11th Street
Completed 2015

Underground Replacement
Replace a stretch of old three phase existing primary underground cable with new along West Milwaukee between Grand Avenue and 2nd Avenue West
Completed 2015

Three Phase Relocation
Three phase underground primary relocation for QRS
Completed 2015

Three Phase Replacement
Three phase padmount transformer relocation for State Steel
Completed 2015

LED Streetlights
Installed around Spencer Hospital
Completed 2015

Three Phase Replacement
Three phase padmount transformer replacement for Tecton
Completed 2015

Three Phase Extension
Three phase UG primary extension for Shine's
Completed 2015

Development
Install new single phase primary underground cable in new development from W 18th St along 22nd Ave W for Fairway Woods First Addition
Completed 2015

New Three Phase
Install new three phase primary underground cable to SMU water well 13 on south side of the airport
Completed 2015

Relocate Three Phase
Relocate three phase primary underground cable and three phase transformer for the Spencer High School Fine Arts Center
Completed 2015

Underground Conversion
Three phase OH to UG primary conversion along 4th Ave SW 400-800 blocks
Completed 2015

Replace Single Phase
Replace single phase underground primary from East 21st Street to East 23rd Street near West Birchwood Estates
Completed 2014

Three Phase Abandonment
Three phase abandonment, single phase conversion between 10th Street SW & Southmoor Drive and 2nd Avenue SW & 4th Avenue SW
Completed 2014

Underground Replacement
Replace a stretch of old  single phase existing primary underground cable with new between 224 8th St SW & 302 8th St SW
Completed 2014

New Underground
Install new three phase primary underground cable along the north side of W 11th St between 11th Ave W and 13th Ave W
Completed 2014

Development
Install new three phase primary underground cable from the Waste Water Treatment plant north to the new building east of Grab & Go for Shine's Third Addition
Completed 2014

Single Phase Loop
Replace a stretch of old  single phase existing primary underground cable with new between 910 Elmwood Dr & 913 E 15th St
Completed 2014

New Underground
Replace a stretch of old three phase existing primary underground cable with new along W 3rd St between 2nd Ave W & 3rd Ave W
Completed 2014

New Three Phase
Install new three phase primary underground cable along the east side of Hwy 71 between 13th St SW & 18 St SW
Completed 2014

Loop Relocation
Replace a stretch of old three phase existing primary underground cable with new along St Lukes Dr between 12th Ave SE & 14th Ave SE near the St. Luke's campus
Completed 2014

New Secondary & Streetlights
Install new secondary cable along with street lights for Spencer's riverfront pier along W Park St & 2nd Ave W
Completed 2014

Three Phase Replacement
Replace a stretch of old three phase existing primary underground cable with new along 32nd Ave W between the Water Plant and W 18th St
Completed 2014

Development
Install new three phase primary underground cable to Holiday Inn Express
Completed 2014

New Three Phase
Install a new three phase transformer for Fairview School and remove the old single phase transformer
Completed 2014